Westco Miljø

industry

1 200 PV-panels covers 2 500 m2

Westco Miljø installed PV-panels on the roof of the recycling station at Forus, summer 2020.

The power of the PV-system is 420 kWp and covers 2 500 square meters.

The PV system consist of 1 200 PV-panels and will produce about 4 000 000 kWh pr year. In the course of a year, this will cover 1/3 of the company’s energy needs, which means that they use less electricity from the grid.

About the project

IndustryIndustry
Year of installation2020
Effect420 kWp
Production per year4 000 000 kWh
CO2 savings per year 

gallery

Click on the picture below to see them bigger