1 200 PV-panels covers 2 500 m2

Westco Miljø installed PV-panels on the roof of the recycling station at Forus, summer 2020.

The power of the PV-system is 420 kWp and covers 2 500 square meters.

The PV system consist of 1 200 PV-panels and will produce about 4 000 000 kWh pr year. In the course of a year, this will cover 1/3 of the company’s energy needs, which means that they use less electricity from the grid.

About the project

Industry Industry
Year of installation 2020
Effect 420 kWp
Production per year 4 000 000 kWh
CO2 savings per year  